Affected services:

  • Internet
  • Network

UPS replacement WZH2

Scheduled for Thursday 7th November 2019 at 22:00 (Zurich)

Schedule/description of work

We will replace the UPS in our data center WZH2. All systems with redundant power supplies will not be affected by this maintenance. The systems without redundant power supplies will be migrated on November 8th between 2:00 AM and 4:00 AM. Those systems will encounter a short service interruption some when between 2:00 AM and 4:00 AM.

Scheduled start time
November 07, 2019 22:00
Duration
7 hours
Status
Finished

Updates

The replacement is finished. We didn't had any unexpected issues.

Posted by René Hildenbrand